The drying hoppers can be started in a staggered manner where the control waits an adjustable
time between starting each drying hopper.
ACS recommends that the customer execute an auto-tune cycle on the regeneration beds and
drying hoppers when the dryer is placed into service for the first time.
The regeneration blower starts.
2
When air flow is verified, the bed in regeneration is brought to the pre-set
regeneration temperature.
The bed remains at the regeneration temperature until either a pre-set time
has expired or the beds outlet air temperature rises above the “Bed Break”
target value at which point the regeneration heaters are turned off and the bed
is allowed to cool for either a pre-set time period or until the bed outlet
temperature reaches the “Cool Down” target value. If the closed loop
regeneration option was purchased, then the closed loop valve will place the
cooling bed into closed loop cooling, as opposed to ambient cooling, when
the bed outlet temperature reaches the “Closed Loop” target value.
A customer adjustable option allows the beds to switch either when the regeneration cycle
completes (“Switch on Time”) or if the dew point rises above a pre-set limit (“Switch on Dew
Point”). The “Switch on Dew Point” option will also cause the beds to switch if a side has been
on-line for an adjustable amount of time.
ACS recommends that the customer execute an auto-tune cycle on the regeneration beds and
drying hoppers when the dryer is placed into service for the first time.
The pattern continues until the dryer is shut down by pressing the “Stop” button on the Dryer
Status screen or the auto start feature reaches a preprogrammed stop event time. However it is
stopped, the DryPro control puts the dryer into a sequenced shutdown.
The drying hoppers process supply air heaters shut down and then the Process air
blower(s) shutdown after an adjustable delay and below an adjustable temperature.
Any running regeneration cycle is allowed to finish and then the regeneration blower
is shutdown.
The dryer can be re-started by pressing the “Restart” button on the Dryer Status
screen.
The Process and regeneration systems run in parallel and independently of each other with the
following exceptions.
2
The Process and regeneration systems start operation in parallel and run independently.
Controls 27